About Project:
A full time Commissioning management team onsite for 20 months.
Commissioning of all HVAC systems in both the Data Centre and Support Areas.
Generation and execution of commissioning test packs.
Two Storey Data Centre Facility of 45MW. The facility will be built over a total of 3 phases with Phase One 9MW and Phase Two and three 18Mw each.
Commissioning Manager Engineer:
Lead Commissioning Engineer:
Lead Water Treatment Engineer:
8No. Commissioning/Water Treatment Team.
Documentation Controller.