About Project:

A full time Commissioning & Water Treatment team onsite for 20 months.
Commissioning of all HVAC systems in both the Data Centre and Support Areas.
Generation and execution of commissioning test packs.

Status
Project Complete
Completion Year
2028
Size

Multi Storey Data Centre Facility of 56MW. The facility will be built over a total of 5 phases with 11.2MW per phase.

Client
Confidential Data Centre, Dublin
Team

Lead Commissioning Engineer:
Lead Water Treatment Engineer:

2No. Commissioning/Water Treatment Team.

testing

Project includes:

Confidential Data Centre, Frankfurt

KES Water Treatment has extensive experience in large scale critical steel pipe work systems flushing and dosing and provide pre-commissioning cleaning of LPHW, CHW, Cooling tower and Process water lines as well as main line and domestic water system sterilizations.