About Project:

A full time Commissioning management team onsite for 12 months.
Commissioning of all HVAC systems in both the Data Centre and Support Areas.
Generation and execution of commissioning test packs.

Status
Project Complete
Completion Year
2026
Size

Two Storey Data Centre Facility of 24MW. The facility will be built over a total of 2 phases with Two Phases of 12Mw.

Client
Confidential Data Centre, Dublin
Team

Lead Commissioning Engineer:
Lead Water Treatment Engineer:

2No. Commissioning/Water Treatment Team.

 

Project includes:

Banner

KES Water Treatment has extensive experience in large scale critical steel pipe work systems flushing and dosing and provide pre-commissioning cleaning of LPHW, CHW systems as well as main line and domestic water system sterilizations.

Water Treatment

HVAC Commissioning